L&M Energy is wishes to provide the following update      regarding its Kaitangata CSG appraisal programme within PEP      38219, located 60km south of Dunedin.
      
The Taratu-1 well is at a current depth of 323m and is      drilling towards an expected total depth of approximately      350m. To date the well has intersected approximately 23m of      the Kai Main coal seam and 12m of the Carson seam between      309m and the current depth. So far a total of 41 canisters of      coal have been gathered for further analysis, including      measurement of gas content and saturation levels.
      
During the week, the Washpool-1 well reached a depth of 219m      before being suspended. The smaller rig being utilised for      the upper portion of the well has been demobilised with the      larger rig mobilising to deepen the well upon completion of      Taratu-1. To date 7.5m of Barclay coal has been intersected      within the Washpool-1 well.
      
Taratu-1 and Washpool-1 are the second and third wells      respectively of a five well programme. The wells are set to      test the coal seam gas potential from five sub-bituminous      coal horizons (Capstick, Jordan, Kai Main, Carson and Shore)      within the coalfield.    
About L&M Energy Limited    
      L&M Energy Limited is a New Zealand based company dual listed      on the ASX and NZX stock exchanges. The Company is focused on      the discovery and development conventional and unconventional      oil and gas resources. The Company holds equity interests in      over 8,200 km2 of exploration acreage contained within eight      New Zealand exploration permits.    